Summary: |
Entry ordered that; NS submit to the Commission and ORDC site plans and cost estimates for the projects by 9/30/04, that by 10/07/04, NS file a letter advising that is has submitted site plans and cost estimates to the Commission and ORDC; that projects to be completed by 6/30/2005; that NS follow the detailed instructions as outlined in the ORDC letter of construction authorization; that NS notify the Commission and ORDC 30 days before the projected date of completion. |
|