Case Title: FIRSTENERGY CORP./EMILY-FOX PROJECT
Status: OPEN-OPEN
Industry Code: EL-ELECTRIC
Purpose Code: BNR-Construction notification report
Date Opened: 12/23/2002
Date Closed:
Printable Docket Card Service List
View All
1 - 4 of 4 documents 1 /  1 
Date FiledSummaryPages
05/10/2005Response to request by the PUCO staff of the Ohio Power Siting Board on the start and completion of construction on several Letter of Notification and Construction Notice filings, filed on behalf of FirstEnergy Service Co. by T. Krauss.3
03/22/2004Letter to Mr. Lambeck that removal of trees would begin on March 22, 2004 and FirstEnergy will begin its construction effort to relocate the Emily-Fox 138kV Transmission Line approximately April 1, 2004 instead of April, 2003 filed on behalf of applicant by T. Krauss.1
01/21/2003Investigation Report approving the construction notice, filed on behalf of PUCO staff by S. Siegfried and E. Smith.1
12/23/2002In the matter of American Transmission Systems, Incorporated ("ATSI") Construction Notice Emily-Fox 138kv Transmission Line relocation project Phase II for the State Route 82 Rd Wildening Project.12
 