CASE NUMBER: 02-3339-EL-BNR
CASE DESCRIPTION: FIRSTENERGY CORP./EMILY-FOX PROJECT
DOCUMENT SIGNED ON: 5/3/2024
DATE OF SERVICE: ________________________________________
05/10/2005 Response to request by the PUCO staff of the Ohio Power Siting Board on the start and completion of construction on several Letter of Notification and Construction Notice filings, filed on behalf of FirstEnergy Service Co. by T. Krauss.
03/22/2004 Letter to Mr. Lambeck that removal of trees would begin on March 22, 2004 and FirstEnergy will begin its construction effort to relocate the Emily-Fox 138kV Transmission Line approximately April 1, 2004 instead of April, 2003 filed on behalf of applicant by T. Krauss.
01/21/2003 Investigation Report approving the construction notice, filed on behalf of PUCO staff by S. Siegfried and E. Smith.
12/23/2002 In the matter of American Transmission Systems, Incorporated ("ATSI") Construction Notice Emily-Fox 138kv Transmission Line relocation project Phase II for the State Route 82 Rd Wildening Project.