DIS - Case Record for 02-2418-EL-BNR Skip to main content

Case Record For:

02-2418-EL-BNR

File a Public Comment
Case Title: FIRST ENERGY CORP/CITY OF MENTOR IN LAKE COUNTY, OHIO
Status: OPEN-OPEN
Industry Code: EL-ELECTRIC
Purpose Code: BNR-Construction notification report
Date Opened: 9/18/2002
Date Closed:
Printable Docket Card Service List
View All
1 - 5 of 5 documents 1 /  1 
Date FiledSummaryPages
08/18/2005Letter stating that construction was completed on August 9, 2005 filed by T. Krauss on behalf of FirstEnergy.1
08/13/2003Letter regarding the construction access pads project filed by T. Krauss.1
10/03/2002Construction notice project area is located within the City of Mentor, Lake County.1
10/03/2002Additional information on behalf of ATSI filed by T. Krauss.10
09/18/2002In the matter of the application of American Transmission Systems, Inc. for a construction notice, Eastlake-Nursery 138 kV Transmission Line & Perry-Eastlake 345 kV Transmission Line, relocation project for the Heisley Road Relocation & Railroad Grade Separation Project.24
 