08/18/2005 | Letter stating that construction was completed on August 9, 2005 filed by T. Krauss on behalf of FirstEnergy. | 1 |
08/13/2003 | Letter regarding the construction access pads project filed by T. Krauss. | 1 |
10/03/2002 | Construction notice project area is located within the City of Mentor, Lake County. | 1 |
10/03/2002 | Additional information on behalf of ATSI filed by T. Krauss. | 10 |
09/18/2002 | In the matter of the application of American Transmission Systems, Inc. for a construction notice, Eastlake-Nursery 138 kV Transmission Line & Perry-Eastlake 345 kV Transmission Line, relocation project for the Heisley Road Relocation & Railroad Grade Separation Project. | 24 |