Finding and Order that by January 11, 2014, NS file a notice that they have initiated with OE or any applicable utility, the process to ensure that electric service will be available at the involved grade crossing as set forth in finding (3); that NS follow the detailed instructions as outlined in the ORDC letter of construction authorization and proceed with and complete the project by September 11, 2014; That NS notify the Commission and ORDC 30 days before the projected date of completion. |
|