Summary: |
Entry ordering that YARR and WE submit to the Commission and ORDC site plans and cost estimates for projects by October 27, 2010; by November 3, 2003 file a notice advising submission; by November 26, 2010 file notice initiating process with AEP to ensure electric service; notify Commission 30 days before the projected date of completion for inspection. |
|