Date Filed:  5/29/2013 5:01:58 PM View Document
Document Type:  MEMO-Memorandum View Document
Link to Document:  View Document
Number of pages:  6
Case Numbers: 
12-1306-RR-STP
Summary: 
During the final inspection, issues were discovered with the train detection system. The system was adjusted and repaired during the inspection. On the basis of the attached final report for the grade crossing project. Staff has determined that the project has been put-in-service. Accordingly, the above case may be closed.