Summary: |
Finding and order that, by May 18, 2012, NS file a notice that it has initiated with Duke the process to ensure that electric service will be available at the involved grade crossing as set forth in finding 3; that NS notify the Commission and ORDC 30 days before the projected date of completion; that at the time Staff or ORDC makes its final inspection, Staff will file a memorandum in this docket indicating the installation is completed and the warning devices have been put in service. |
|