Summary: |
Finding and order ordered that by March 3, 2015, CSX file notice that it has initiated with AEP,
Toledo Edison, or any applicable utility, the process to ensure that electric service will
be available at the involved grade crossings, ordered that NS and WLE follow the detailed instructions as outlined in the
ORDC letter of construction authorization and proceed with and complete the projects
by November 3,2015. |
|