Summary: |
Finding and ordered, That by February 9,2019, WLE file notice that it has initiated with OEC, or any applicable utility, the process to ensure that electric service will be available at the involved grade crossing as set forth in Paragraph 8. It is, further, ordered, That WLE follow the detailed instructions as outlined in the ORDC letter of construction authorization and proceed with and complete the project by October 9,2019. |
|