Summary: |
Finding & Order stating that by June 3, 2017, CSX file notice that it has initiated with PPS, or any applicable utility, the process to ensure that electric service will be available at the involved grade crossing as set forth in Paragraph 8; that the project be completed by February 3, 2018; that CSX notify Staff and ORDC of any changes in the scope of work, cost overruns, materials, etc. |
|