Summary: |
Order on certificate amendment ordered that the certificate of environmental compatibility and public need for the 08-170 electric transmission line project is hereby amended to permit the relocation of the portion of the line as described in this order, subject to the additional conditions set forth by Staff in its report of September 30, 2010. (OPSB) |
|