Summary: |
Entry ordering that CSX's request for extension of time be granted and that CSX complete the project by August 4, 2010; follow detailed instructions as outlined in the ORDC letter of construction authorization and notify Staff at least 5 working days before the date work is scheduled to begin at the project site so arrangements can be made for inspection. |
|