Summary: |
Entry ordered that CSX acquire materials for and proceed with the installation of the crossing project set forth above. It is further ordered that CSX strictly comply with all directives and procedures set forth herein as well as with all applicable federal procedures in connection with the installation project and that the installation project be completed at this crossing no later than January 4, 1997. (4 pgs.) |
|