Summary: |
Construction Notice stating that construction on the 138 kV Transmission Line Installation at the Bayshore Substation Project, which was approved on September 28, 2013, commenced on February 17, 2014
and construction was complete on May 28, 2014 filed on behalf of FirstEnergy Service Company by N. Bryksenkova. |
|