Summary: |
Entry ordering that NS submit to the Commission and ORDC site plans and cost estimates for the project by August 24, 2010; by August 31, 2010, NS file a letter stating it has submitted site plans and cost estimates; by September 23, 2010, NS file notice that it has initiated with the applicable public utility; by May 26, 2011, the project must be complete. |
|