Date Filed:  9/27/2012 3:10:15 PM View Document
Document Type:  TX-Text View Document
Link to Document:  View Document
Number of pages:  1
Case Numbers: 
10-2787-RR-RCP
Summary: 
Letter informing the Commission that the Columbus &. Ohio River Railroad (CUOH) install new light and gate assemblies at the N Cedar St/SR 79 grade crossing in conjunction with ODOT roadway work and traffic signal installation and preemption at the SR 79/SR16 on and off ramp. The ordered completion date for the project was September 8, 2011. By subsequent Entries, the deadline for this project was extended to October 1, 2012. filed by Staff.