Summary: |
Opinion, Order, and Certificate ordered, That the Stipulation be approved and adopted. It is, further, ordered, That a certificate be issued to Vinton for the construction, operation, and maintenance of the electric generation facility, subject to the conditions set forth in the Stipulation and this Order. It is, further, ordered, That the motion for protective order filed by Vinton be granted. It is, further, ordered, That the Commission's Docketing Division maintain, under seal, the financial information contained on pages 29-31 of the application narrative; Ex. B,