DIS - Document Record Skip to main content

Document Record

Date Filed:  9/20/2018 2:30:31 PM View Document
Document Type:  OO-Opinion & Order View Document
Link to Document:  View Document
Number of pages:  35
Case Numbers: 
17-0774-EL-BGN
Summary: 
Opinion, Order, and Certificate ordered, That the Stipulation be approved and adopted. It is, further, ordered, That a certificate be issued to Vinton for the construction, operation, and maintenance of the electric generation facility, subject to the conditions set forth in the Stipulation and this Order. It is, further, ordered, That the motion for protective order filed by Vinton be granted. It is, further, ordered, That the Commission's Docketing Division maintain, under seal, the financial information contained on pages 29-31 of the application narrative; Ex. B, Item 5, the GE Inverter manufacturer's specification documents; and Ex. J, the policy numbers and certificate number. It is, further, ordered, That this protective order shall be effective for a period of 24 months from the date of this Order.
Source File(s):