Summary: |
Finding and Order that by January 24, 2019, WE submit to the Commission's Railroad Division site plans and cost estimates for the project and by January 31, 2019 file a letter advising site plans and cost estimates have been submitted to the Commission. Following approval, WE proceed with and complete the project by October 24, 2019. |
|