Summary: |
Opinion & Order issuing a certificate of environmental compatibility and public need to Firelands Wind, LLC for the construction, operation, and maintenance of an 8.7-mile long 345 kilovolt transmission line in Huron and Erie counties, Ohio along the preferred route, subject to the conditions set forth in the Stipulation and consistent with this Opinion, Order, and Certificate. electronically filed by Ms. Mary E. Fischer on behalf of the Ohio Power Siting Board. |
|