Summary: |
Entry, ordered that a comprehensive investigation of the costs incurred and the management decisions made during the construction of the Perry Nuclear Power Station shall be performed; Ordered that RFP No. U85-1 be distributed by July 26, 1985 to retain qualified indepent consultants to assist the staff in this investigation; Ordered that the CEI Co. shall reimburse the Commission for the costs of this investigation and shall make appropriate arrangements with the Commission for such reimbursement; Ordered that a copy of this Entry be served upon persons in 840188-EL-AIR & 84-414-EL-AAM. |
|