Summary: |
Finding and ordered, That by October 26, 2018, NS file notice that it has initiated with HWEC, or any applicable utility, the process to ensure that electric service will be available at the involved grade crossing as set forth in Paragraph 8. It is, further, ordered, That NS follow the detailed instructions as outlined in the ORDC letter of construction authorization and proceed with and complete the project by September
26,2019. It is, further, ordered, That NS notify Staff and ORDC at least five working days before the date work is scheduled to begin at the project site so that arrangements can be made for any inspection. |
|