Summary: |
Entry ordered that NS submit to the Commission and ORDC site plans and cost estimates for the project by March 6, 2007; that by March 13, 2007, NS file a letter to this docket administration that it has submitted site plans and cost estimates to the Commission and ORDC; that following approval of site plans and cost estimates by ORDC, NS proceed with construction of the project, with construction to be completed by December 6, 2007; that NS follow the detailed instructions as outlined in the ORDC letter of construction authorization; that NS notify the Commission and ORDC 30 days before the projected date of completion ordered that at the time staff or ORDC makes its final inspection and if it finds that the installation at the grade crossing is completed and has been put in service, staff will file a memorandum in this docket directing the docketing division to close this case of record. |
|