Summary: |
Entry ordered that W&LE and CSX submit to the Commission and ORDC site plans and cost estimates for the projects by August 24, 2007, ; that following approval of site plans and cost estimates by ORDC, WE&LE and CSX proceed with and complete the project by May 24, 2008. |
|