Summary: |
ICN #0022 Letter stating that construction of Columbia's Columbus Northwest High Pressure Pipeline Extension, Phase I, began on September 9, 1991; that the pipeline was placed in service and began commercial operation on October 31, 1991; and that construction of the project was completed on November 7, 1991, filed on behalf of applicant by K. Christman. |
|