Summary: |
Entry ordering that IOCR and IORY submit to the Commission and ORDC site plans and cost estimates for the projects within 90 days of the date of this entry; that IOCR and IORY proceed with construction of the projects, to be completed by March 21, 2003; that IOCR and IORY notify the Commission's railroad section upon completion of each project, at which times Commission staff will make its final inspections and file a memorandum in this docket directing the Docketing Division to close this case of record. |
|