Summary: |
Entry ordered that NS submit to the Commission and ORDC site plans and cost estimates for the projects by January 4, 2007; that by January 11, 2007, NS file a letter in this docket advising that it has submitted site plans and cost estimates to the Commission and ORDC; that following approval of site plans and cost estimates with construction of the projects with construction to be completed by October 4, 2007; that NS follow the detailed instructions as outlined in the letter on construction authorization; that NS notify the Commission and ORDC 30 days before the projected date of completion; that at the time staff of ORDC makes its final inspection and if it finds that the installations at the grade crossing are completed and have been put in service, staff will notify docketing to close the case of record. |
|