Summary: |
Finding and Order ordering that by September 22, 2018, NS file notice that it has initiated with OEC or any applicable utility, the process to ensure that electric service will be available at the involved gate crossing as set forth in Paragraph 8 and that NS follow the detailed instructions as outlined in the ORDC letter of construction authorization and proceed with and complete the project by May 22, 2019. |
|