Summary: |
Entry ordering that the agreement be adopted by the Commis- sion; that the Railroad submit to the Commission site plans and cost estimates for the project within 90 days of the date of this entry; that the Railroad proceed with con- struction of the project as set forth in tghe agreement, with construction to be completed by April 16, 2000. (3 pgs.) |
|