Summary: |
Order on Rehearing that the complainant's first assignment of error is moot and second assignment of error is granted; that the Commission's February 17, 1999 decision is modified inpart such that the request for two-way, nonoptional, measured-rate EAS between the Wilmot and Sugar Creek ex- changes is granted; that two-way, nonoptional, measured-rate EAS between the Wilmot and Sugar Creek exchanges be insti- tuted within six months of this order and GTE make every effort to provide the service as soon as praticable; that GTE extablishas in-service date within two months of this Order on Rehearing, inform the Commission and the spokes- persons for the complainants of the date, and advise the Commission and the spokespersons no later than 60 days prior to the in-service date in the event that a date cannot be met; that this case be closed of record. (6 pgs.) |
|