CASE NUMBER: 99-1491-RR-STP
CASE DESCRIPTION: ASHLAND RAILWAY
DOCUMENT SIGNED ON: 5/10/2024
DATE OF SERVICE: ________________________________________
08/31/2001 Memo stating that the projects have been put in service and, therefore, this case may be closed, filed by L. Dalton, PUCO staff.
04/03/2000 Construction authorization and field report filed by B. Johrendt, PUCO staff.
12/09/1999 Entry ordering that the stipulation submitted by the parties be approved; that Ashland Rail submit, within 90 days of the date of the date of this entry, project site plans and costs estimates for Commission approval. (3 pgs.)
12/09/1999 - Entry ordering that the stipulation submitted by the parties be approved; that Ashland Rail submit, within 90 days of the date of this entry, project site plans and costs estimates for Commission approval. (3 pgs.)
11/16/1999 In the matter of a request for the modenization to roadway gates with flashing lights at Main Street/SR39/96(152-184W), City of Shelby, Richland County, Ashland Railway. (13 pgs)