10/11/2001
|
Entry closing cases this case of record. |
09/27/2001
|
Memorandum recommending that the legal staff proceed with an entry to close this case of record, filed by L. Dalton, PUCO staff. |
05/04/2000
|
Entry ordering that the request for an extension be granted and that the project should be completed no later than Octo- ber 31, 2000. (2 pgs.) |
05/04/2000
|
Entry ordering that the request for an extension be granted and that the project should be completed no later than Octo- ber 31, 2000. |
04/04/2000
|
Entry ordering that the completion date for this project be extended until May 26, 2000. (AE) (1 pg.) |
03/21/2000
|
Memo filed by B. Johrendt, PUCO staff, with attached request for extension of time for project completion filed by R. Frederick, CSX Transportation. |
03/21/2000
|
Memo filed by B. Johrendt, PUCO staff, with attached request for extension of time for project completion filed by R. Frederick, CSX Transportation. (2 pgs.) |
04/30/1999
|
Service Notice |
04/29/1999
|
Entry ordering that the agreement is adopted by the Commis- sion; that Conrail complete the projects identified in the agreement within 12 months of the date of this entry; that Conrail submit for Commission approval site plans and cost estimates for the projects within 90 days of the date of this entry. (4 pgs.) |
04/15/1999
|
In the matter of a request for the installation of flashing lights and roadway gates and surface at a newly constructed grade crossing and the closure at Davis Street (532-650A), Mary Street (532-648Y), and Lousia Street (532-647S), Vil- lage of Forest, Hardin County, Consolidated Rail Corp. (16 pgs.) |