Date Filed | Summary | Pages |
07/01/1999 | Electric fuel component rider (sheet No. 40) and Table of Contents filed on behalf of applicant by K. Turosky. (4 pgs.) | 4 |
06/22/1999 | Opinion & Order that the EFC rate to be charged by Ohio Edison for jurisdictional customer bills rendered during the company's next annual EFC period of July 1, 1999 through June 30, 2000 shall be 1.3567c/kWh; that Ohio Edison file its EFC tariff rider incorporating this EFC rate by June 30, 1999, to become effective on July 1, 1999, and remain in effect until otherwise ordered by the Commis- sion. (4 pgs.) | 4 |
06/09/1999 | Transcript filed for hearing held 5/25/99, (RB), 10 pgs., Submitted. (PUCO-Columbus, OH) | 10 |
05/25/1999 | Exhibit 1 filed on behalf of OCC by C. Mooney. (2 pgs.) | 2 |
04/23/1999 | Annual EFC review submitted by PUCO staff. (5 pgs) | 5 |
04/22/1999 | Finding & Order scheduling a hearing on May 25, 1999, at the Commission offices; pre-hearing data will be due 3/30/99; audit report will be due 4/23/99. (9 pgs.) | 9 |
03/30/1999 | 30-day filing information filed on behalf of applicant by J. Burk. (3 pgs.) | 3 |
01/15/1999 | In the matter of the regulation of the electric fuel component contained within the rate schedule of Ohio Edison and related matters. | 1 |