10/05/2001
|
Memo closing this case of record. |
01/12/1999
|
ICN #0005 Letter stating that construction for this project is scheduled to start on January 11, 1999, filed on behalf of applicant by G. Cunningham. (1 pg.) |
09/30/1998
|
Response to Letter of Notification filed by K. Wissman, PUCO staff. |
09/24/1998
|
Investigation report submitted by: J. Odell. (1 pg.) |
09/24/1998
|
Investigation Report, Letter of Notification, filed by J. O'Dell. |
09/18/1998
|
ICN #0002 Correspondence letters to various people regarding the application, filed on behalf of applicant by T. Burgess. (6 pgs.) |
09/18/1998
|
ICN #0001 In the matter of the Letter of Notification of FirstEnergy Corp. involving the construction of a 0.2 mile double circuit, 138 kV transmission line loop from the Iron- ville-Jackman 138 kV transmission line into the proposed Chrysler/Jeep 138-12.47 kV substation. (20 pgs.) |