10/05/2001
|
Memo closing this case of record. |
05/27/1999
|
Letter stating completion date was December 1, 1998. Submitted by: J.E. Schrader (AEP) (1 pg.) |
05/11/1999
|
ICN #0005 Comments regarding the Letter of Notification filed on behalf of applicant by J. Schrader. (2 pgs.) |
09/01/1998
|
Letter stating that construction on the project is scheduled to start September 28, 1998, filed on behalf of applicant by J. Heppner. |
05/01/1998
|
ICN #0003 Response to James E. Schrader to Letter of Notifi- cation, filed by K. Wissman, PUCO staff. (1 pg.) |
04/30/1998
|
ICN #0002 Investigation report approving the Letter of Notifcation, filed by R. Yerian, PUCO staff. (1 pg.) |
03/31/1998
|
ICN #0001 In the matter of the Letter of Notification of Columbus Southern Power Company for the proposed West Lancaster-Bixby 138 kV Line, Tap to South Central Power's proposed Pickerington Road distributions station. (28 pgs.) |