Date Filed | Summary | Pages |
10/05/2001 | Memo closing this case of record. | 2 |
06/08/1999 | Letter stating that construction was completed on April 22, 1999 filed on behalf of applicant by J.E. Schrader. (1 pg.) | 1 |
05/27/1999 | Letter stating the completion date of April 22, 1999. Submitted by: J.E. Schrader (AEP) (1 pg.) | 1 |
05/11/1999 | ICN #0010 Comments regarding the Letter of Notification filed on behalf of applicant by J. Schrader. (2 pgs.) | 2 |
03/01/1999 | ICN #0009 Letter stating that construction on this project is scheduled to start on March 1, 1999, filed on behalf of applicant by J. Schrader. (1 pg.) | 1 |
06/16/1998 | ICN #0008 Letter stating that construction on this project is scheduled to start on June 1, 1998, filed on behalf of applicant by J. Schrader. (1 pg.) | 1 |
05/21/1998 | ICN #0007 Response to Letter of Notification, filed by K. Wissman, PUCO staff. (1 pg.) | 1 |
05/21/1998 | ICN #0006 Investigation report approving the Letter of Notification, filed by L. Winget, PUCO staff. (1 pg.) | 1 |
05/18/1998 | ICN #0005 Revised Letter of Notification filed on behalf of applicant by J. Schrader. (28 pgs.) | 28 |
04/27/1998 | Letter of notification for Vine-City of Columbus (East), 138 KV Relocation; construction scheduled to start 5/4/98 filed by J. Schrader. (1 pg) | 1 |
02/04/1998 | ICN #0003 Letter to Mr. J. E. Schrader, American Electric Power, in response to Letter of Notification, filed by K. Wissman, PUCO staff. (1 pg.) | 1 |
01/23/1998 | ICN #0002 Investigation report approving the Letter of Notification, filed by L. Winget, PUCO staff. (1 pg.) | 1 |
01/07/1998 | ICN #0001 In the matter of Letter of Notification of Colum- bus Southern Power Company for a 0.24 mile relocation of the existing Vine-City of Columbus(East) 138kV to accommodate the Nationwide Arena Facilities. (23 pgs.) | 24 |