CASE NUMBER: 97-1590-EL-BLN
CASE DESCRIPTION: CEI/EASTLAKE-NURSERY
DOCUMENT SIGNED ON: 10/6/2024
DATE OF SERVICE: ________________________________________
10/05/2001 Memo closing this case of record.
08/05/1998 ICN #0007 Letter stating that construction for this project was completed on July 30, 1998, filed on behalf of applicant by G. Cunningham. (1 pg.)
03/31/1998 ICN #0006 Letter stating that construction started on this project on March 18, 1998, filed on behalf of applicant by G. Cunningham. (1 pg.)
01/22/1998 ICN #0005 Response from the Ohio Historic Preservation Office filed by R. Malinowski. (2 pgs.)
01/05/1998 ICN #0004 Comments filed on behalf of the City of Mentor by J. Suso. (1 pg.)
12/24/1997 ICN #0003 Investigation report approving the Letter of Notification, filed by J. O'Dell, PUCO staff. (1 pg.)
12/24/1997 ICN #0002 Response to Letter of Notification filed by K. Wissman, PUCO staff. (1 pg.)
12/04/1997 ICN #0001 In the matter of the Letter of Notification of The Cleveland Electric Illuminating Company regarding the reconductoring of the 138kV Eastlake-Nursery transmission circuits to serve a customer (Painseville Municipal Sys- tem). (16 pgs.)