Date Filed | Summary | Pages |
10/05/2001 | Memo closing this case of record. | 2 |
02/27/1998 | ICN #0007 Letter informing the Commission that construction on this project was completed on February 13, 1998, filed on behalf of applicant by A. Musko, Jr. (1 pg.) | 1 |
10/15/1997 | ICN#0006 Letter stating start date for construction will be the week of Oct. 27, 1997 filed on behalf of applicant by T. Krauss. (1 pg.) | 1 |
09/19/1997 | ICN #0005 Correspondence letter, with attached letter from Martha J. Raymond, Department Head, Ohio Historical Pre- servation Office, filed on behalf of applicant by T. Krauss. (2 pgs.) | 2 |
09/02/1997 | ICN #0004 Copy of letter from Kent E. Kroonemeyer of the United States Department of the Interior, Fish and Wild- life Service regarding the Toledo Edison Bay Shore to Bay Shore Junction, filed on behalf of applicant by T. Krauss. (2 pgs.) | 2 |
08/25/1997 | ICN #0003 Investigation report approving the Letter of Notification, filed by J. O'Dell, PUCO staff. (1 pg.) | 1 |
08/22/1997 | ICN #0002 Response to Letter of Notification filed by K. Wissman, PUCO staff. (1 pg.) | 1 |
08/07/1997 | ICN #0001 In the matter of the Letter of Notification of The Toledo Edison Company's Bay Shore to Bay Shore Junc- tion, D Transmission Line Second Circuit Project, Lucas County, Ohio. (22 pgs.) | 22 |