10/11/2001
|
Entry closing cases this case of record. |
09/27/2001
|
Memorandum recommending that the legal staff proceed with an entry to close this case of record, filed by L. Dalton, PUCO staff. |
12/28/1998
|
Entry ordering that the project site plans and cost esti- mates submitted by Conrail are approved; that Conrail com- plete the project installation by October 30, 1999. (AE) (2 pgs.) |
12/22/1998
|
Program letter filed on behalf of the PUCO staff by B. Johrendt. (3 pgs.) |
08/06/1998
|
Entry ordering that the agreement be adopted by the Commis- sion; that the Railroad submit for Commission approval site plans and cost estimates for the projects within 90 days of the date of this entry. (4 pgs.) |
07/09/1998
|
Subsidy agreement and authorization for preliminary engineering for this project filed on behalf of the Ohio Rail Development Commission by T. O'Leary; Ohio Department of Transportation by T. Wray; Village of Bremen by T. Harper; Conrail by R. Cantwell; and the PUCO staff by A. Agler. (9 pgs.) |
03/05/1997
|
In the matter of a request for a Consolidation Project, with the installation of active warning devices at Broad Street/ SR 664 (513-422L) and the closure (to vehicular traffic) of an Alley (513-421E), Village of Bremen, Fairfield County, Consolidated Rail Corp. (5 pgs.) |