CASE NUMBER: 96-0388-EL-BTX
CASE DESCRIPTION: DP&L/SHELBY SUBSTATION
DOCUMENT SIGNED ON: 5/7/2024
DATE OF SERVICE: ________________________________________
03/31/1998 ICN #0019 Letter stating that this project was completed in August, 1996, and can be closed out, filed on behalf of applicant by R. Lewis. (2 pgs.)
12/23/1996 ICN #0018 Letter advising the Commission that construction of this project was completed on December 19, 1996, filed on behalf of applicant by H. Shamash. (1 pg.)
10/10/1996 ICN #0017 Engineering drawings filed on behalf of applicant by H. Shamash. (1 pg.)
10/10/1996 ICN #0016 Letter advising the Commission that DP&L plans to commence construction on the subject project on October 10, 1996, filed by H. Shamash. (1 pg.)
10/08/1996 ICN #0015 Letter to Mr. Hertzel Shamash stating that the engineering drawings for this project have been reviewed by the staff and applicant may proceed with construction, filed by K. Wissman, PUCO staff. (1 pg.)
10/07/1996 Opinion, Order and Certificate ordering that the joint stip- ulation and recommendation filed in this case be approved in it entirety it is further ordered that a certificate of environmental compatibility and public need is hereby issued to the Dayton Power and Light Company for the construction, operation, and maintenance of the Shelby substation expans- ion project at the preferred site. (AE) (13 pgs.)
09/18/1996 Transcript filed for hearing held 9/11/96, (SD), 8 pgs., Submitted. (Columbus, OH-PUCO)
09/17/1996 ICN #0012 Transcript filed for hearing held 9/10/96, (SD),` 6 pgs. (Sidney, Ohio)
08/27/1996 ICN #0011 Staff Report filed. (33 pgs.) (FILED 8/26/96)
07/18/1996 ICN #0010 Entry scheduling a nonadjudicatory hearing at 7:00 p.m. on 9/10/96 at the Pasco United Methodist Church, Sid- ney, Ohio; scheduling an adjudicatory hearing at 1:30 p.m. on 9/11/96 at the Commission offices. (AE) (3 pgs.)
07/18/1996 ICN #0009 Responses to requests for information received from the Ohio Power Siting Board Staff, filed on behalf of applicant by E. Rizer. (97 pgs.)
07/02/1996 ICN #0008 Ohio Power Siting Board Staff's combined requests for production of documents and interrogatories, first set, filed by P. Colbert. (11 pgs.)
06/13/1996 ICN #0007 Proof of service filed on behalf of applicant by E. Rizer. (5 pgs.)
06/04/1996 ICN #0006 Letter to Mr. Hertzel Shamash regarding the application, filed on behalf of the PUCO staff. (2 pgs.)
06/03/1996 ICN #0005 Letter in support of DP&L's proposed system improvement and associated power siting application, filed on behalf of Honda of America Mfg., Inc. by E. Fryman. (1 pg.)
05/23/1996 ICN #0004 Letter supporting the application, filed by R. Byrne, Buckeye Power, Inc. (2 pgs.)
05/13/1996 ICN# 003 Entry ordering that the request of The Dayton Power and Light Company for waivers of both the one-year notice requirement of section 4906.06(A), revised code, and the requirement of rule 4906-5-03(B), O.A.C., for fully developed information on an alternate route be granted. (3 pgs.)
04/22/1996 ICN #2 Request for waiver of the one year before construction notice requirement filed on behalf of applicant by E. Rizer. (2 pgs.)
04/22/1996 ICN #1 In the matter of the Dayton Power and Light Company's expansion of the Shelby Substation to accommodate additional circuit breakers.