01/19/2001
|
Memo closing this case of record. |
07/24/1996
|
ICN #0005 Letter stating that construction on this project was completed and the line was energized on June 27, 1996, filed on behalf of applicant by A. Musko, Jr. (1 pg.) |
04/15/1996
|
Letter stating that the planned date of initial construction is April 18, 1996 filed by A. Musko, Jr. on behalf Centerior Energy. |
04/01/1996
|
Letter from Kim Wissman, PUCO, to M. Regulinkski, stating that the requested waiver of the 90 filing time period is granted. |
03/28/1996
|
Staff report filed. |
03/18/1996
|
In the matter of the Letter of Notification of Toledo Edison Company for the Delafoil 138kV Supply Line Project. |
|