DIS - Case Record for 96-0128-EL-BLN Skip to main content
      
      
CASE NUMBER: 96-0128-EL-BLN
CASE DESCRIPTION: COLUMBUS SOUTHERN POWER/SCIPPO LINE
DOCUMENT SIGNED ON: 4/16/2024
DATE OF SERVICE: ________________________________________
01/19/2001 Memo closing this case of record.
05/16/1996 ICN #0006 Letter stating that construction on this project was completed on the week of May 6, 1996, filed on behalf of applicant by J. Schrader. (1 pg.)
05/16/1996 ICN No. 0006, Letter to Mr. Glazer advising that construction on project was completed the week of May 6, 1996, filed by J. Schrader.
04/04/1996 ICN No. 0005, Letter to Mr. Glazer notifying that construction on project is scheduled to start the week of April 10, 1996, filed by J. Schrader.
04/04/1996 ICN #0005 Letter advising the Commission that construction on this project is scheduled to start the week of April 10, 1996, filed on behalf of applicant by J. Schrader. (1 pg.)
02/20/1996 ICN No. 0004, Letter to Mr. Schrader regarding letter of notification, informing them that the filing meets the informational requirements, filed on behalf of OPSB by K. Wissman.
02/20/1996 ICN #0004 Response to J. E. Schrader to Letter of Notifi- cation, filed by K. Wissman, PUCO staff. (1 pg.)
02/15/1996 ICN No. 0003, Letter of Notification filed by J. O'Dell.
02/15/1996 ICN #0003 Investigation report approving the Letter of Notification, filed by J. O'Dell, PUCO staff. (1 pg.)
02/14/1996 ICN No. 0002, Letter to Chairman Glazer requesting a waiver of this 90 day notice requirement so we can start construction in time to meet customers needs, filed on behalf of applicant by J. Schrader.
02/14/1996 ICN #0002 Letter requesting a waiver of the 90 day notice requirement, filed on behalf of applicant by J. Schrader. (1 pg.)
02/07/1996 ICN #0001 In the matter of the Letter of Notification of Columbus Southern Power Company for the proposed Scippo- E. Scippo 138 Kv Line. (37 pgs.)