01/19/2001
|
Memo closing this case of record. |
08/01/1996
|
ICN No. 0005, letter informing the Commission that the project was completed and the line was energized on July 22, 1996, filed on behalf of applicant by A. Musko. |
06/06/1996
|
ICN #0005 Letter stating that the subject project has been completed and was energized on May 30, 1996, filed on behalf of applicant by H. Shamash. (1 pg.) |
02/22/1996
|
Letter to Ms. Wissman notifying of construction to begin on February 29, 1996, filed on behalf of applicant by H. Shamash. |
02/22/1996
|
ICN #0004 Letter stating that applicant plans to begin construction on February 29, 1996, filed by H. Shamash. (1 pg.) |
02/15/1996
|
ICN No. 0003, Response to Letter of Notification filed on January 29, 1996, filed on behalf of OPSB by K. Wissman. |
02/15/1996
|
ICN #0003 Letter to Hertzel Shamash in response to Letter of Notification, filed by K. Wissman, PUCO staff. (1 pg.) |
02/14/1996
|
ICN No. 0002, Investigation Report, Letter of Notification, filed on behalf of PUCO by J. O'Dell. |
02/14/1996
|
ICN #0002 Investigation report approving the Letter of Notification, filed by J. O'Dell, PUCO staff. (1 pg.) |
01/29/1996
|
In the matter of the application of The Dayton Power and Light Company to construct approximately 1.12 miles of new 138kV transmission line in southern Miami Co. to provide a new power source to the Company's New Carlisle Distribution substation and thereby reduce the loading on other facilities. |
01/29/1996
|
Letter of Notification to construct The New Carlisle 138 kV tap line in Miami County, Ohio. (46 pgs.) |