06/22/1999 | Entry closing this case of record. (2 pgs.) | 2 |
06/11/1999 | Memo closing this case of record. (1 pg.) | 1 |
03/26/1997 | Entry ordering that the site plans and costs estimates for this project be approved under the conditions set forth in the ORDC memo; that Conrail complete the project as quickly as possible, but in any event not later than December 5, 1997. (AE) (2 pgs.) | 2 |
03/18/1997 | duplicate Program letter, encumbrance estimate, Form ODOT-LF07DT70, and design plans for the Stark County crossing, filed by B. Johrendt, PUCO staff. | 7 |
03/18/1997 | Program letter, encumbrance estimate, Form ODOT-LF07DT70, and design plans for the Stark County crossing, filed by B. Johrendt, PUCO staff. (7 pgs.) | 7 |
12/05/1996 | Entry ordering that the stipulation be approved, and that Conrail complete these projects as set forth in Finding 3; that Conrail submit to the Commission's Transportation Department, Railroad Section, within 90 days of the date of this entry, project site plans and cost estimates for Commission approval. (3 pgs.) | 5 |
11/19/1996 | duplicate Subsidy agreement signed on behalf of Ohio Rail Development Commission; Ohio Department of Transportation by T. Wray; Tuscarawas Township by D. Kennedy; Conrail by G. Thelen; and the PUCO staff by A. Agler. | 11 |
11/19/1996 | Subsidy agreement signed on behalf of Ohio Rail Development Commission; Ohio Department of Transportation by T. Wray; Tuscarawas Township by D. Kennedy; Conrail by G. Thelen; and the PUCO staff by A. Agler. (11 pgs.) | 11 |
01/12/1996 | In the matter of the request of the modernization to roadway gates at Beaumont/T344 {502-695A) and the closure to vehicles at Boyd's Corner Road (502-696G), Tuscarawas Township, Stark County. | 5 |