04/23/1998
|
Entry closing this case of record. (1 pg.) |
03/02/1998
|
Final reports, findings, conclusions and recommendations filed on behalf of the PUCO staff by B. Johrendt. (5 pgs.) |
10/29/1996
|
Entry ordering that the site plans and costs estimates sub- mitted by Conrail are approved; that Conrail complete in- stallation of the Fisher Road project as quickly as possible by in any event not later than nine months from the issuance of this entry. (AE) (2 pgs.) |
10/25/1996
|
Memo, with attached information from Conrail, stating that the revised site plans and cost estimates have been received and recommending that the Legal Department generate an entry authorizing construction, filed by B. Johrendt, PUCO staff. (12 pgs.) |
07/26/1996
|
Entry ordering that the project site plans and costs estimates submitted by Conrail are approved and that Conrail proceed with the installation of the projects under the conditions set forth in the July 19, 1996 staff memorandum it is further order that the installation of the projects be completed no later than July 26, 1997. (AE) (2 pgs.) |
07/22/1996
|
Findings filed on behalf of the PUCO staff by B. Johrendt. (3 pgs.) (Alton Darby Creek Rd., Cole Rd., Doherty Rd.) |
07/22/1996
|
Findings filed on behalf of the PUCO staff by B. Johrendt. (2 pgs.) (Fisher Road, Columbus, Ohio) |
03/21/1996
|
Entry approving stipulation and ordering that Conrail submit within 90 days of the date of this entry project site plans and costs estimates for commission approval. (3 pgs.) |
03/06/1996
|
Subsidy agreement filed on behalf of Conrail by J. Cossel; the PUCO staff by A. Agler; and Franklin County by J. Cur- ile. (8 pgs.) |
12/04/1995
|
In the matter of a request of the installation of active warning devices at Cole Rd., Doherty/T273, Alton-Darby Rd., and the modernization to roadway gates at Fisher Rd., Franklin County, Conrail. (6 pgs.) |