01/19/2001
|
Memo closing this case of record. |
05/07/1998
|
ICN #0006 Letter stating that the Wheeling Pittsburgh Steel Corp. Electric Transmission Line was completed on April 30, 1998, filed on behalf of applicant by J. McCann. (1 pg.) |
10/24/1997
|
ICN #0005 Letter stating that the projected completion date is now scheduled for September 1998, filed on behalf of applicant by J. Schiffer, P.E. (1 pg.) |
12/08/1995
|
Letter stating that applicant did not include sufficient data to compute the electric and magnetic fields filed by L. E. Winget, PUCO staff. (3 pgs.) |
12/05/1995
|
Letter stating Letter of Notification meets requirements and the project may proceed filed by K. Wissman, PUCO staff. (1 pg.) |
12/04/1995
|
ICN #0002 Investigation report approving the Letter of Notification, filed by J. O'Dell, PUCO staff. (1 pg.) |
11/21/1995
|
ICN #0001 In the matter of the Letter of Notification of National Power Exchange Group, Inc., Mingo Junction Energy Center Partnership, for the Wheeling-Pittsburgh Steel Corporation Electric Transmission Line Project. (39 pgs.) |