01/19/2001
|
Memo closing this case of record. |
08/16/1996
|
ICN #0006 Letter informing the Commission that construction on this project was completed and the line was energized on July 27, 1996, filed on behalf of applicant by T. Den- zler. |
08/16/1996
|
ICN #0006 Letter informing the Commission that construction on this project was completed and the line was energized on July 27, 1996, filed on behalf of applicant by T. Den- zler. (1 pg.) |
03/28/1996
|
ICN #0005 Letter informing the Commission that the planned date of initial construction is the week of April 1, 1996, filed on behalf of applicant by T. Denzler. |
03/28/1996
|
ICN #0005 Letter informing the Commission that the planned date of initial construction is the week of April 1, 1996, filed on behalf of applicant by T. Denzler. (1 pg.) |
12/22/1995
|
ICN #0004 Letter in response to Letter of Notification, filed by K. Wissman, PUCO staff. (1 pg.) |
12/21/1995
|
ICN #0003 Investigation report approving the Letter of Notification, filed by J. O'Dell, PUCO staff. (1 pg.) |
12/15/1995
|
ICN #0002 Letter of Notification filed on behalf of applicant by M. Regulinski. (2 pgs.) |
11/13/1995
|
ICN #0001 In the matter of the Letter of Notification of Toledo Edison Company for the I-75 Improvement Project. (22 pgs.) |