DIS - Case Record for 95-0603-RR-FED Skip to main content
      
      
CASE NUMBER: 95-0603-RR-FED
CASE DESCRIPTION: CONRAIL/CITY OF MARIETTA
DOCUMENT SIGNED ON: 11/22/2024
DATE OF SERVICE: ________________________________________
02/10/1997 Entry ordering that the site plans and costs estimates for these projects be approved under the conditions set forth in this entry and that CSX complete the projects as quickly as possibly, but in any event not later than November 11, 1997. (AE) (3 pgs.)
01/29/1997 Program letter, job number authorization, and encumbrance estimate for the CSX Transportation, Consolidation Project, Washington County, City of Marietta, filed by B. Johrendt, PUCO staff. (7 pgs.)
01/11/1996 Entry adopting the subsidy agreement by the Commission; that Conrail submit for Commission approval site plans and cost estimates for the project within 90 days of the date of this entry. (3 pgs.)
12/18/1995 Subsidy agreement filed on behalf of CSX Transportation; ODOT by T. Wray; City of Marietta by R. Boesne; the PUCO staff by A. Agler; CSX Transportation by C. Hardy. (7 pgs.)
06/27/1995 In the matter of the installation of active warning devices at Grove Ave. and the closure of vehicular traffic at Barber Ave. and Pearl St., City of Marietta, Washington County, Consolidated Rail Corp. (6 pgs.)