01/19/2001
|
Memo closing this case of record. |
06/21/1995
|
ICN #0007 Letter stating construction has been completed filed by J. E. Schrader. (1 pg.) |
03/17/1995
|
ICN #0006 Letter stating that construction of this project will start on March 27, 1995, filed on behalf of applicant by J. Schrader. (1 pg.) |
03/09/1995
|
ICN #0005 Letter to J. E. Schrader in response to Letter of Notification filed by K. Wissman, OPSB staff. (1 pg.) |
03/08/1995
|
ICN #0004 Investigation report approving the Letter of Notification, filed by J. O'Dell, OPSB staff. (1 pg.) |
02/24/1995
|
ICN #0003 Response letter to Joyce Schramm filed on behalf of the OPSB staff by K. Wissman. (2 pgs.) |
02/24/1995
|
ICN #0002 Correspondence letter objecting to the appli- cation, filed by J. Schramm. (1 pg.) |
01/24/1995
|
ICN #0001 In the matter of the Letter of Notification of Columbus Southern Power Company for the proposed Roberts- Davidson-Bethel 138kV project. (54 pgs.) |